Timeline
Our Work
Project Timeline
Planning and Funding / Finance
Investigate location by conducting pre-feasibility study
Define purpose and estimate massing
Submit Letter of Intent to apply for funding for full feasibility study
By December 1st, 2021
Design
Develop systems diagrams
Construct conceptual design with UW Facilities Engineering Services process partners
Feasibility Study
Request funding for feasibility study ($12,000), for
1) surveying the land and investigating geotechnical considerations ($7,000), and
2) any additional potential costs we may incur in completing a feasibility study, including hiring technical experts on an as needed basis ($5,000)
By February 7th, 2022
If needed, apply for additional funding for permitting, hiring technical expertise
By April 1st
Develop schematic and detailed design
Consult the UW Design Review Board
Pursue necessary permitting
Form a Request for Proposal (RFP)
Use cost estimate developed with UW PDG to submit request to CSF for full project cost funding
Likely by December 1st, 2022
Job Order Contract (JOC) for construction
Outline a 12-week span for construction to take place during appropriate building window (includes start-up pieces, lining up labor, trenching, etc.)
Likely during Spring - Summer 2023
Get Involved
Contact us to join this project or learn more about the work we are doing with the UW Farm.
Contact
Resiliency
Tunnel
Contact US
Vision
Structure
Site
About Us
TimeLine
Menu